Once we had the slab for the tent and the tent, the next step was to build restroom adjacent to the tent. We started the restrooms by putting in water and sewer lines out to the street. It’s over 1100 feet to the street-that’s pretty far!
Then we started the building, with the footer, plumbing in the floor, and walls.
Then trusses and the roof.
We put stucco over the block walls and put in windows to match the house and carriage house.